Construction process
Regarding the interior construction time, it will be completed depending on the current status of the apartment and the items to be constructed:
- The normal progress from the company's side meets
- Apartment interior construction: 25-30 days.
- Villas - townhouses 25-30 days or more
- Office interior construction: From 10 - 20 working days or more.
- Showroom interior construction: From 25 to 40 working days or more
- Hotel and Restaurant interior construction: Construction time depends on the design documents for each specific stage.
The construction stage will be paid in 2 installments
Apply for construction permit, deposit with project management board (if necessary)
Usually, interior construction of apartments or townhouses will require a permit from the building management board or neighborhood management board. It will take from a few days to 1 week.
Construction
Basic steps in the construction phase:
- New construction/ fundament renovation
- Demolition or/and construction, installation, tiling
- Construction of electricity and water, plaster ceiling, painting
- Production and installation of furniture
- Installation at the construction site
- Completion and cleaning
- Contract payment, acceptance, handover of completed property to customer and sending warranty certificate
Moment is always proactive in the production of furniture/architecture. The factory uses modern machinery and equipment, professional control processes along with high skills of the factory staff.